Power Outage Scheduled Over Winter Break

12/08/2023

by Buffy Lockette

Crews working on the university's ongoing construction projects will make the most of winter break, using the campus closure to complete work that requires power to be shut off to some buildings, listed below. Internet service will also be unavailable to affected buildings when the power is out. 

Affected Buildingsgettyimages-877083556.jpg

  • CEPS Complex, including Child Development Center and Center for Manufacturing Support
  • Computer Center
  • Curtiss Hall
  • Daugette Hall 
  • Fitzpatrick Hall
  • Hammond Hall and Anders Roundhouse
  • Jack Hopper Dining Hall
  • Kennamer Hall
  • Leone Cole Auditorium 
  • Mason Hall (music)
  • Rec Center
  • Salls Hall
  • Stephenson Hall
  • Theron Montgomery Building
  • Visitors dressing room of JSU Stadium 

Timeline for Power Outage

Dec. 20: Power off at 7 a.m. and restored between 4-6 p.m. 
Dec. 21: Power off at 7 a.m. and restored between 4-6 p.m. 
Dec. 22: Power off at 7 a.m. and restored between 4-6 p.m. 
Dec. 23-25: Power restored fully. 
Dec. 26: Power shut off at 7 a.m. until work is complete.
Dec. 27: Power off all day and night
Dec. 28: Power off all day and night
Dec. 29: Power off in morning and restored in the afternoon.

The contractors will work diligently to have power restored as quickly as possible. Thank you for your patience as these necessary upgrades and improvements are implemented.