Project Information

Timeline

Construction of the new Recreation and Fitness Center is in response to the JSU strategic plan to enhance the quality of campus life and to recruit and retain students.
  • 2016: Brailsford & Dunlavey engaged with JSU to plan, design, and construct the new Recreation Center.
  • September 23, 2016: Paul Brailsford, co-founder and CEO of Brailsford & Dunlavey, and Jeff Sessine, Senior Vice President of Centers, present to the JSU Board of Trustees.
  • January 2017: BOT unanimously approves proposal to build a new 101,000 square foot fitness and wellness center through a public private partnership with the JSU Foundation.
  • July 24, 2017: CENTERS begins management of current recreation operation.
  • September 23, 2017: Ground breaking ceremony held for new Recreation Center.
  • April 10, 2018: Turner Construction holds “topping out” ceremony to celebrate the construction milestone.
  • Spring 2019: Anticipated Opening.

Project Funding

The facility is a $32.5M, 101,000 square foot recreation center developed through a public private partnership (P3) with the JSU foundation. The JSU rec center will be the second higher education student recreation facility in the country ever built under a P3 structure. The project was designed to minimize costs to students and will be completed within the capital limits supported by a $190 per semester student fee. The recreation fee was supported by students and approved by the JSU Board of Trustees. The fee will be implemented when the facility opens in Spring 2019